11 06, 2026

POWER HOUR – Power Supply Report

By |2026-06-11T09:27:21+02:00June 11, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:
Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.
Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.
In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.
Collectively, these improvements provide a sound basis for the positive energy availability outlook.
11 06, 2026

POWER HOUR – Power Supply Status

By |2026-06-11T09:26:55+02:00June 11, 2026|Comments Off on POWER HOUR – Power Supply Status

 

NOTE:

Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

11 06, 2026

⚡️POWER HOUR – Power Supply Report

By |2026-06-11T09:26:33+02:00June 11, 2026|Comments Off on ⚡️POWER HOUR – Power Supply Report

NOTE:
Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.
Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

11 06, 2026

POWER STATUS UPDATE

By |2026-06-11T09:26:08+02:00June 11, 2026|Comments Off on POWER STATUS UPDATE

NOTE:
Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.
Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

11 06, 2026

POWER HOUR – Power Supply Report

By |2026-06-11T09:25:31+02:00June 11, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:
Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.
Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.
In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.
Collectively, these improvements provide a sound basis for the positive energy availability outlook.
4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:22:13+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

 

NOTE:

Reliabilitychallengespersistonunitsthathavenotyetundergoneremediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Keyperformancemetricshave,however,improvedmaterially.MeanTimeto Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

Inaddition,MeanTimeBetweenFailures(MTBF)hasincreased,withunitsnow remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively,theseimprovementsprovideasoundbasisforthepositiveenergy availability outlook.

4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:21:04+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:

Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

 

4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:20:36+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:

Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:18:55+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:

Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:18:20+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:

Reliabilitychallengespersistonunitsthathavenotyetundergoneremediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Keyperformancemetricshave,however,improvedmaterially.MeanTimeto Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

Inaddition,MeanTimeBetweenFailures(MTBF)hasincreased,withunitsnow remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively,theseimprovementsprovideasoundbasisforthepositiveenergy availability outlook.

Go to Top