4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:22:13+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

 

NOTE:

Reliabilitychallengespersistonunitsthathavenotyetundergoneremediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Keyperformancemetricshave,however,improvedmaterially.MeanTimeto Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

Inaddition,MeanTimeBetweenFailures(MTBF)hasincreased,withunitsnow remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively,theseimprovementsprovideasoundbasisforthepositiveenergy availability outlook.

4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:21:04+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:

Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

 

4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:20:36+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:

Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:18:55+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:

Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

4 03, 2026

POWER HOUR – Power Supply Report

By |2026-03-04T15:18:20+02:00March 4, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:

Reliabilitychallengespersistonunitsthathavenotyetundergoneremediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Keyperformancemetricshave,however,improvedmaterially.MeanTimeto Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

Inaddition,MeanTimeBetweenFailures(MTBF)hasincreased,withunitsnow remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively,theseimprovementsprovideasoundbasisforthepositiveenergy availability outlook.

5 02, 2026

POWER HOUR – Power Supply Report

By |2026-02-05T09:13:04+02:00February 5, 2026|Comments Off on POWER HOUR – Power Supply Report

NOTE:

Reliability challenges persist on units that have not yet under gone remediation. As a result, forced outages and short-duration (“pit-stop”) maintenance interventions will continue to be undertaken based on plant condition.

Key performance metrics have, however, improved materially. Mean Time to Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

In addition, Mean Time Between Failures (MTBF) has increased, with units now remaining on the grid longer for an average of 120 days before a failure occurs.

Collectively, these improvements provide a sound basis for the positive energy availability outlook.

1 02, 2026

Power Hour – Thursday 29/01/26 Power Supply Summary

By |2026-02-01T21:26:07+02:00February 1, 2026|Comments Off on Power Hour – Thursday 29/01/26 Power Supply Summary

NOTE:
  •  Keyperformancemetricshave,however,improvedmaterially.MeanTimeto Repair (MTTR) has been reduced from approximately 30-50 days to 12 days.

Go to Top